Steer clear of roadwork – ODOT outlines construction

Southbound Interstate 75, between Ohio 281 and Bays Road, will experience lane restrictions for slide repair. Estimated completion: November.

Northbound Interstate 75 ramp to Interstate 80/90 Ohio Turnpike (Exit 195B) may experience lane restrictions for bridge work. Estimated completion: October.

U.S. Route 6, between Rudolph Road and State Route 235, Bowling Green, will experience lane restrictions for resurfacing through November. Future restrictions may be announced for improvements at Route 6 and Route 235 intersection. Estimated completion: summer 2021.

  • U.S. Route 6, between State Route 235 and Range Line Road, is open following pavement repair.

State Route 25, between Ohio 582 and Roachton Road may experience lane restrictions for final striping and finish work. Estimated completion: October.

State Route 64, between East Main Street and South Church Street, Haskins, will be closed for railroad repairs beginning Tuesday, Oct. 20, for approximately 7 days. Work performed by railroad. Detour: Route 582 to Route 65 to Route 64

State Route 64/Waterville Bridge replacement – Route 64 may experience lane restrictions for bridge work over the Maumee River. Memorial Park in Waterville is closed. Estimated completion: November.

State Route 65 at King Road, Haskins, will be closed for pavement repair beginning Monday, Oct. 26, through Friday, Oct. 30. Detour: Route 582 to Route 64 to Route 65

State Route 65 at Lime City Road, Rossford, is closed through mid-October for work by the city of Rossford. 

State Route 235, between Avery Road and Euler Road, Weston, will be closed for railroad repairs beginning Thursday, Oct. 22 for approximately 7 days. Work performed by railroad. Detour: Route 6 to Route 65 to Route 281

State Route 582, between Dunbridge Road and Carter Road, Dunbridge, is closed for railroad repairs through mid-October. Detour: I-75 to Route 105 to Route 199

State Route 582, between Luckey Road and Stoney Ridge Road, Luckey, will be closed for a culvert replacement beginning Monday, Oct. 19, through mid-November. Detour: US 23 to Route 105 to Route 199

All work is weather permitting.