West Wooster waterline upgrades done; sewer line replacements continue

Westbound lane to remain closed while West Wooster work continues.

Work continues to progress on the West WoosterStreet/Haskins Road water and sewer improvement project in Bowling Green. The contractor has completed 100% of the waterline upgrades and 25% of the sewer line replacement portion of this project.

As work continues to progress, intermittent lane restrictions and closures along West Wooster Street and Haskins Road can be expected and restrictions at intersections may be necessary. 

After the water and sewer improvements have been completed, the curbs will be replaced and the trenches will be paved along West Wooster and Haskins Road throughout the project area. 

Current estimates indicate the water and sewer project will be completed by early August. Upon completion of the water and sewer project, a separate contractor will complete a full-width milling and paving project along West Wooster Street and Haskins Road.

This schedule is dependent upon weather and progress of work.