The repaving along Conneaut Avenue is progressing. Currently the contractor has finished much of the work associated with the concrete crosswalks and driveway accesses as well as repairing the waterline trench located west of Wintergarden. The following is tentatively scheduled for the beginning of next week:
• Monday (July 31): pavement will be installed from Mitchell to Haskins; driveways from Maple to Grove will be removed along with certain driveways on Fairview; curb installation along Conneaut from Haskins to Grove.
• Tuesday (Aug. 1): continue pavement installation from Mitchell to Haskins; pour concrete driveway approaches and crosswalk ramps.
This schedule is dependent upon weather and progress of work. Questions about this project may be directed to the Engineering Division at 419-354-6227.