The 2022 Bowling Green paving projects will soon begin. The first of these projects will be the paving of East Wooster, from Campbell Hill Road to just west of the railroad tracks.
During this work, one lane of traffic will be maintained in each direction with intermittent closure of drive approaches and intersections. It is anticipated that this work will begin in mid-July.
The contract completion date for this project is October 2022. This schedule is dependent upon weather and progress of work.
The other portions of the 2022 paving projects are those associated with the use of ARPA funds and the paving of residential roads. The removal and replacement of curbs, ADA ramps, and certain sections of sidewalk has already begun, with paving efforts to begin late August.
The contract completion date for this project is October 2022. This schedule is dependent upon weather and progress of work.
Portions of the following roads are scheduled to be paved as part of this project: Clough, North and South Enterprise, West Evers, Frazee, Lehman, Leroy, Mitchell, Pike, North Prospect, East and West Reed, Ridge, and South Summit.
Mayor Mike Aspacher and City Council previously allocated approximately $3 million of ARPA funds towards paving of residential roads throughout the city. This will occur over a three-year period – 2022, 2023, and 2024.