Downtown Wooster Street pavement rehab nearly complete

The planned Wooster Street pavement rehabilitation work downtown is nearly complete. The contractor has removed and replaced portions of the concrete road base and plans to begin placing the intermediate course of asphalt next week.

Once the intermediate asphalt is placed, temporary striping will occur and the road will open completely to traffic, including parking, and the traffic lights will resume operation.

Concrete repairs along the sidewalks and ADA ramps throughout the project area will continue. The contractor has finished the majority of these repairs along the east side of Main Street and has begun making repairs on the west side of Main Street. These repairs will also occur on Wooster Street.

Once complete, the final surface course of asphalt will be applied. Paving is anticipated to last through October. The timeline above is dependent upon progress of work and weather. Continued patience with the ongoing construction is appreciated.

Questions about this work may be directed to the Engineering Division at 419-354-6227.