Gas line replacement project progressing on west side of BG

Columbia Gas signs for work along Haskins Road

Columbia Gas is continuing the gas line replacement project in Bowling Green. All of the new mainline has been installed. Service line replacements are about 70% complete. Crews are working this week on Wallace Street and the other side streets off Haskins Road.

Permanent restoration will follow once the installations are complete.

Anyone with questions may contact Ben Cutler, Columbia Gas public affairs specialist, at 216.215.4103 (call/text) or Bcutler@nisource.com.