After long wait, West Wooster Street, Haskins Road paving will begin next week

Utility upgrades on West Wooster Street are completed.

The installation of the water and sewer mains along West Wooster Street and Haskins Road has been completed – and soon the paving will begin. 

Beginning Tuesday, Sept. 12, the contractor responsible for paving the final driving surface, will begin milling the top three inches of roadway and will replace it with new asphalt from curb to curb along West Wooster Street between Church Street and Haskins Road, and Haskins Road, between West Wooster and Parker Street. 

The intersections at Poe Road and Wallace Avenue will be completed during this timeframe as well. Intermittent lane closures should be expected as this work progresses. 

It’s expected that this project will be completed by the end of the month. Completion date is dependent on weather and progress of work.

Follow along with this and other capital improvement projects on the city’s Capital Improvement Map, which can be found on the city’s website: www.bgohio.org.