Downtown construction moving next to North Church Street

Downtown waterline in Bowling Green in 2019.

The contractor in downtown Bowling Green has progressed west along West Wooster Street with the installation of a replacement water line.

Beginning Monday, this work will continue onto North Church Street. Through Tuesday, North Church will be inaccessible from West Wooster.

The East Wooster Street portion of this work is tentatively scheduled to begin toward the end of next week. This will include the area from Main to Prospect. During this work, eastbound traffic along East Wooster will be maintained while the westbound lane of traffic will be closed.

The utility portion of this project is anticipated to last through the spring of 2019. Once complete, a contractor will repave the downtown.

Questions about this may be directed to the city’s engineering division at 419-354-6227.