The Ohio Department of Transportation has listed new projects and updates about ongoing projects in the Wood County area. Among them are:
Interstate 75, between US 6 and Poe Road, Bowling Green, may experience lane restrictions for overhead bridge demolition on Poe Road and Gypsy Lane Road.
Continuing Work
- Gypsy Lane Road, between Campbell Hill Road and Dunbridge Road, is closed for bridge replacement through August. Detour: Campbell Hill Road to Napoleon Road to Dunbridge Road.
- Poe Road, between Mercer Road and Dunbridge Road, is closed for bridge replacement through August. Detour: Mercer Road to Ohio 64 to Dunbridge Road.
U.S. 6, between Ohio 281 and Pemberville Road, Bradner, is open following railroad work.
Route 6, between Van Tassel Road and Range Line Road, Weston, will experience lane restrictions for pavement widening and drainage work near Ohio 235. Estimated completion: July 15.
Ohio 25/Dixie Highway, between Ohio 582 and King Road, Perrysburg Township, will experience lane restrictions for construction of a turn lane beginning Monday, July 5, through July.
Ohio 65, between Ovitt Road and Route 64, Middleton Township, will be closed for a culvert replacement beginning Tuesday, July 6. Estimated completion: July 23. Detour: Route 65 to Route 582 to Route 64 to Route 65.
Ohio 199, between Route 6 and Elm Street, West Millgrove, may experience lane restrictions for microsurfacing. Estimated completion: Sept. 1.
Ohio 235, between Euler Road and Willow Road, Weston, is open following pavement widening and drainage work.
Ohio 795 at Lemoyne Road, Millbury, may experience lane restrictions for signal replacement.