Water & sewer board approves projects

From NORTHWESTERN WATER & SEWER DISTRICT

The Northwestern Water and Sewer District is moving forward on several new projects passed by the Board of Trustees on January 26, 2017.  This list includes:

Perrysburg Township: Starbright Subdivision Waterline Replacement 
The board approved an estimated $900,000 project to replace the waterline in the Starbright subdivision and surrounding areas.  The project will be advertised for bid within eight weeks.  Work is expected to begin this spring.  This project will impact residential roadways and properties within the subdivision and on Oregon Road near State Route 795.  Detailed information will be announced this spring.

Rossford: Lorraine Place Sanitary Sewer Replacement
The board approved an estimated $128,755 project to upgrade the sanitary sewer lines on Lorraine Place.  The project will be advertised for bid this February.  The district expects no major interference with property or roadways due to the nature of construction.

Detailed District Board of Trustees Minutes at:
http://www.nwwsd.org/about/board-of-trustees/agendasminutes/

Other District Updates:
Residents of Millbury will be receiving a letter over the next few weeks regarding an upcoming sanitary sewer and pump station capital improvement project. The prime contractor, Visu-Sewer, will begin work on this $1 million project in March.  Most work will occur in the roadway, but there may be instances where backyard access is needed.  More information will be announced prior to the start of the project.